Submeasure „Dryer for sewage sludge with waste heat recovery“
![Klaerschlammtrockner Sustreat 1](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-1.jpg)
On 12th February 2013, the torso of the dryer has been installed into the former storehouse for sewage sludge.
![Installation of the torso](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-2.jpg)
Installation of the torso
![Klaerschlammtrockner Sustreat 3](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-3.jpg)
November 2014: Beginning of the installation of the heating system
![Continuous operation of the drying plant since October 2015](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-12.jpg)
Continuous operation of the drying plant since October 2015
![Continuous operation of the drying plant since October 2015](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-13.jpg)
Continuous operation of the drying plant since October 2015
![August 2015: Completion of the heating system](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-9.jpg)
August 2015: Completion of the heating system
![Completion of the switching system](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-10.jpg)
Completion of the switching system
![07.09.2015: Erster Versuch der Trocknung von Koblenzer Klärschlamm](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-11.jpg)
07.09.2015: Erster Versuch der Trocknung von Koblenzer Klärschlamm
![Technical installation on the storage vessel for sewage sludge](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-7.jpg)
Technical installation on the storage vessel for sewage sludge
![June 2015: Installation of the switch cabinet for the dryer](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-8.jpg)
June 2015: Installation of the switch cabinet for the dryer
![March 2015: The assembly of the sewage sludge dryer has been finished except for the pipeline isolation.](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-6.jpg)
March 2015: The assembly of the sewage sludge dryer has been finished except for the pipeline isolation.
![March 2015: The assembly of the sewage sludge dryer has been finished except for the pipeline isolation.](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-5.jpg)
March 2015: The assembly of the sewage sludge dryer has been finished except for the pipeline isolation.
![Presentation of the sewage sludge drying plant in operation by the project manager Mr Marquart](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-19.jpg)
Presentation of the sewage sludge drying plant in operation by the project manager Mr Marquart
![chemical exhaust air treatment](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-14.jpg)
chemical exhaust air treatment
![Setup of the silos for thermally dried sludge on 16th December 2014.](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-4.jpg)
Setup of the silos for thermally dried sludge on 16th December 2014.
![Keynote speaker State Secretary Dr. Griese as bearer of the greeting message from the Ministry of the Environment](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-16.jpg)
Keynote speaker State Secretary Dr. Griese as bearer of the greeting message from the Ministry of the Environment
![Official commissioning by the plant manager of the sewage treatment plant, Mr Keßelheim](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-17.jpg)
Official commissioning by the plant manager of the sewage treatment plant, Mr Keßelheim
![Official commissioning by the project partner IB Götzelmann+Partner, Mr Hölle](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-18.jpg)
Official commissioning by the project partner IB Götzelmann+Partner, Mr Hölle
![Speaker of the building department Prüm at the official commissioning ceremony on 10 November 2015](https://sustreat.eu/wp-content/uploads/2020/03/klaerschlammtrockner-sustreat-15.jpg)
Speaker of the building department Mr. Prüm at the official commissioning ceremony on 10 November 2015